If you have noticed lately, browounts not only happen daily but longer at that.

According to SOCOTECO 2, this is due to the Preventive Maintenance Shutdown for the STEAG State Power Inc. (SPI) Mindanao Coal Fire-Powered Plant’s two electric generation units from October 6, 2012 to November 10, 2012.

SPI’s power plant is considered the biggest and most modern in Mindanao Island on a per unit capacity.  It has already  delivered more than 8.3 billion kilowatt  hours (kwh) of electricity representing about 20% of Mindanao’s total power supply.

Due to its preventive maintenance shutdown, there will be a shortfall in the delivery of electricity to Mindanao’s electric cooperatives, including SOCOTECO II… and thus, the 2.5 hours daily brownouts that GenSan is undergoing now.

Here then is Socoteco 2′s schedule of browounts for October 11, 2012.  You may scroll down to read further.  You may also enlarge the document by clicking the “+” sign.